Udyo Logo

Udyo

Get the Udyo Mobile App

Sign in to save your progress and access all features.

Cabinet Approves ₹9,450 Crore Railway Multitracking Projects

The Cabinet Committee on Economic Affairs (CCEA), chaired by Prime Minister Narendra Modi, has approved four multitracking railway projects spanning 410 km across West Bengal, Odisha, Tamil Nadu, and Andhra Pradesh. Scheduled for completion by 2030-31 with a budget of ₹9,450 crore, these projects will enhance freight capacity by 76 MTPA, boost connectivity to key ecological and tourist hubs, and align with the PM-Gati Shakti National Master Plan to minimize logistics costs and carbon emissions.

What Happened

On August 19, 2026, the Cabinet Committee on Economic Affairs (CCEA) approved four major multitracking railway projects covering a total distance of 410 km. With a total outlay of ₹9,450 crore, these projects aim to alleviate rail network congestion and increase operational efficiency. The capacity enhancement will heavily focus on improving the transportation of essential commodities like coal, iron ore, and cement.

When & Where

The projects will be executed across eight districts located in four eastern and southern states: West Bengal, Odisha, Tamil Nadu, and Andhra Pradesh. They involve critical economic and coastal corridors and are targeted to be completed by the financial year 2030-31.

Who Is Involved

  • Cabinet Committee on Economic Affairs (CCEA): Chaired by the Prime Minister, the final approving authority for the expenditure.
  • Ministry of Railways: The nodal implementation ministry responsible for executing the 410 km multitracking projects.
  • State Governments: West Bengal, Odisha, Tamil Nadu, and Andhra Pradesh will be involved in land acquisition and local clearances.

How It Works

1. Capacity Augmentation: The deployment of 3rd and 4th parallel lines on highly congested routes allows separation of freight and passenger traffic.
2. PM-Gati Shakti Integration: Integrated planning under this master plan avoids siloed infrastructure development and ensures smooth multi-modal logistics connectivity.
3. Freight Mobilization: The designated corridors will serve as essential routes for bulk commodities, adding a capacity of 76 MTPA (Million Tonnes Per Annum).
4. Decarbonization: Electrified rail transport replaces road trucking, reducing crude oil dependence and curbing CO2 emissions massively.

Why It Matters

These projects are critical for India's GS Paper 3 (Infrastructure and Economic Development) syllabus. Economically, they will lower the national logistics cost, making domestic manufacturing competitive. Environmentally, they support India's climate goals by cutting CO2 emissions equivalent to planting 2.60 crore trees. Socially, the enhanced connectivity links remote ecological sites (like Bhitarkanika and Pulicat Lake) to mainstream tourist maps, boosting local employment.

Historical Background

  • 1853: Indian Railways began its journey, establishing the core transport network of the nation.
  • 2017: The Railway Budget was merged with the Union Budget, giving a major push to capital expenditure in the sector.
  • 2021: The PM-Gati Shakti National Master Plan was launched to break departmental silos and promote integrated infrastructure planning.

Previous Related Events

  • August 2023: The CCEA approved seven multi-tracking railway projects worth ₹32,500 crore to expand the network by 2,339 km.
  • February 2024: The Interim Union Budget announced three major economic railway corridors (energy, mineral, and cement corridors).
  • March 2025: Indian Railways achieved 100% electrification of its broad-gauge network.

Static GK Connection

  • Cabinet Committee on Economic Affairs (CCEA): An extra-constitutional body chaired by the Prime Minister that reviews economic trends and directs major investments.
  • Pulicat Lake: The second largest brackish water lagoon in India (after Chilika), located on the border of Andhra Pradesh and Tamil Nadu.

India & World Comparison

India holds the fourth-largest railway network in the world (after the US, China, and Russia). However, India's logistics cost remains around 13-14% of its GDP, which is significantly higher than the global average of 8-10% in developed nations. Projects like these aim to bridge that efficiency gap.

Future Impact

The completion of these projects by 2030-31 will make the eastern coastal rail corridor deeply robust for port-led development. The addition of 76 MTPA freight capacity will stabilize commodity prices and ensure rapid evacuation of coal and minerals. In the long term, this sets a strong foundation for India's transition to achieving its "Net Zero" carbon emission targets by 2070.


🔑 Key Points for Revision

  • The CCEA approved four railway multitracking projects worth ₹9,450 crore.
  • The projects will add 410 km of new tracks across four states.
  • Target completion deadline for the infrastructure projects is 2030-31.
  • States covered: West Bengal, Odisha, Tamil Nadu, and Andhra Pradesh.
  • Longest approved segment: Kharagpur–Bhadrak (Ranital) 4th Line (173 km).
  • Other segments: Bhadrak–Haridaspur (75 km), Gummidipundi–Gudur (90 km), Cuttack–Paradeep (72 km).
  • Freight capacity will be permanently augmented by 76 MTPA.
  • Projects align directly with the PM-Gati Shakti National Master Plan.
  • Environmental impact: ~13 crore litres of oil import reduced.
  • Climate goal aid: CO2 emissions lowered by ~65 crore kg.
  • Ecological connectivity boosted: Pulicat Lake, Bhitarkanika National Park, Kuldiha Wildlife Sanctuary.
  • Cultural connectivity boosted: Panchalingeswar Temple, Maa Bhadrakali temple.
  • Supports the vision of an "Atmanirbhar" New India through job creation.
  • Crucial for moving coal, iron ore, and food grains.
  • Nodal executing body: Ministry of Railways.

🧠 Concept Link (Static GK Deep Dive)

Core Concept: PM-Gati Shakti National Master Plan

  • Definition: A digital platform bringing 16 Ministries together for integrated planning and coordinated implementation of infrastructure connectivity projects.
  • Constitutional / Legal Basis: Executive policy framework (not a statutory act), heavily linked to Article 77 (Conduct of Business of the Government of India).
  • Scientific / Economic Principle: Capitalizing on "Multi-modal connectivity" to reduce bottlenecks, lower logistics costs, and improve turnaround times.
  • How it connects to this event: The ₹9,450 crore railway projects are planned precisely on this platform to ensure seamless cargo movement.
  • Origin & History: Launched on October 13, 2021, by the Prime Minister of India.
  • Key milestone 1: Integration of over 1000 data layers of central and state governments by 2022.
  • Key milestone 2: Used effectively to map the three economic railway corridors announced in 2024.
  • Related Acts / Schemes / Treaties: National Infrastructure Pipeline (NIP), Bharatmala, Sagarmala.
  • Nodal Ministry / Body: Department for Promotion of Industry and Internal Trade (DPIIT) under the Ministry of Commerce and Industry.
  • India-specific relevance: Essential for India to reduce its logistics costs from 13% of GDP to global standards of 8%.
  • Global comparison: Similar to China’s Belt and Road Initiative (domestically) or the USA's interstate highway and multi-modal logistics frameworks.
  • Data point: Aimed to monitor and execute projects worth over ₹100 lakh crore.
  • Common exam angle: UPSC frequently asks about the pillars of Gati Shakti, its digital portal nature, and its impact on the economy.
  • Easy memory hook: "Gati Shakti" = Speed (Gati) and Power (Shakti) for India's infrastructure.

❓ Practice MCQs

Q1. The CCEA recently approved four railway multitracking projects at a cost of ₹9,450 crore. By which year are these projects targeted for completion? [Easy]

A) 2027-28

B) 2028-29

C) 2030-31

D) 2035-36

Answer: C

Explanation: The total estimated cost of the projects is ₹9,450 crore and they are targeted to be completed by 2030-31.


Q2. Which of the following states is NOT covered under the recently approved 410 km railway multitracking projects? [Easy]

A) West Bengal

B) Odisha

C) Tamil Nadu

D) Karnataka

Answer: D

Explanation: The projects cover eight districts in West Bengal, Odisha, Tamil Nadu, and Andhra Pradesh, excluding Karnataka.


Q3. The Gummidipundi–Gudur 3rd and 4th line project connects which two states? [Moderate]

A) Odisha and West Bengal

B) Andhra Pradesh and Tamil Nadu

C) Telangana and Andhra Pradesh

D) Tamil Nadu and Kerala

Answer: B

Explanation: The 90 km Gummidipundi–Gudur 3rd and 4th line connects the states of Andhra Pradesh and Tamil Nadu.


Q4. The capacity augmentation works of these multitracking railway projects will result in additional freight traffic of what magnitude? [Moderate]

A) 50 MTPA

B) 65 MTPA

C) 76 MTPA

D) 100 MTPA

Answer: C

Explanation: The capacity augmentation works will result in additional freight traffic of magnitude 76 MTPA (Million Tonnes Per Annum).


Q5. The implementation of these multitracking projects is expected to reduce CO2 emissions by approximately how much? [Moderate]

A) 25 Crore Kg

B) 40 Crore Kg

C) 65 Crore Kg

D) 80 Crore Kg

Answer: C

Explanation: The projects will lower CO2 emissions by ~65 crore kg, which is equivalent to the plantation of 2.60 crore trees.


Q6. Which of the following ecological sites will see improved rail connectivity as a direct result of these approved railway corridors? [Tricky]

A) Keoladeo National Park

B) Pulicat Lake

C) Chilika Lake

D) Vembanad Lake

Answer: B

Explanation: The capacity enhancement will improve connectivity to several destinations including Pulicat Lake, Bhitarkanika National Park, and Kuldiha Wildlife Sanctuary.


Q7. What is the length of the Kharagpur–Bhadrak (Ranital) 4th Line approved by the CCEA? [Tricky]

A) 72 km

B) 75 km

C) 90 km

D) 173 km

Answer: D

Explanation: The Kharagpur–Bhadrak (Ranital) 4th Line is the longest of the four projects, spanning 173 km across West Bengal and Odisha.


Q8. Under which overarching national framework are these railway projects being planned to ensure multi-modal connectivity? [Easy]

A) Bharatmala Pariyojana

B) PM-Gati Shakti National Master Plan

C) Sagarmala Programme

D) Setu Bharatam

Answer: B

Explanation: The projects are meticulously planned on the PM-Gati Shakti National Master Plan with a focus on enhancing multi-modal connectivity and logistic efficiency.


📜 Previous Year Question Style (PYQ)

PYQ 1:

With reference to the PM-Gati Shakti National Master Plan, often seen in the news in relation to railway and road infrastructure projects, what is its primary objective?

A) To provide free public transportation across major metropolitan cities.

B) To ensure integrated planning and synchronized implementation of infrastructure projects across ministries.

C) To privatize all existing Indian Railway corridors by 2030.

D) To completely replace coal-based freight transit with renewable energy alternatives.

Answer: B

Explanation: PM-Gati Shakti aims at integrated planning and breaking departmental silos to enhance multi-modal connectivity and logistics efficiency.


PYQ 2:

Consider the following wildlife and geographical sites mentioned in the context of eastern coastal railway corridors:

1. Bhitarkanika National Park
2. Pulicat Lake
3. Kuldiha Wildlife Sanctuary

Which of the above destinations are located in the state of Odisha?

A) 1 and 2 only

B) 2 and 3 only

C) 1 and 3 only

D) 1, 2, and 3

Answer: C

Explanation: Bhitarkanika and Kuldiha are located in Odisha, whereas Pulicat Lake is situated on the border of Andhra Pradesh and Tamil Nadu.


PYQ 3:

Assertion (A): The expansion of multitracking railway corridors significantly helps in achieving national climate goals.

Reason (R): Railways are an energy-efficient mode of transport, and shifting freight from road to rail reduces oil imports and cuts carbon dioxide emissions.

A) Both A and R are true and R is the correct explanation of A.

B) Both A and R are true but R is not the correct explanation of A.

C) A is true but R is false.

D) A is false but R is true.

Answer: A

Explanation: Expanding rail capacity allows more freight to be transported via an energy-efficient medium, directly cutting oil dependency and CO2 emissions as cited in the government approval notes.


✍️ Mains Answer Pointers

Question 1 (150 words): Discuss the significance of multi-tracking railway corridors in reducing India's logistics deficit and promoting environmental sustainability.

The recent Cabinet approval of ₹9,450 crore for four multitracking railway projects covering 410 km underscores the critical role of railway infrastructure in India’s economic growth. Economically, adding 3rd and 4th lines to heavily congested corridors separates passenger and freight traffic. This guarantees faster turnaround times for bulk commodities like coal and iron ore, bringing additional freight traffic of 76 MTPA. By augmenting this capacity under the PM-Gati Shakti master plan, India can significantly lower its high logistics costs, making domestic goods globally competitive. Environmentally, the shift of heavy freight from road to electrified rail pathways promotes sustainability. These 410 km projects alone are projected to reduce oil imports by approximately 13 crore litres and cut CO2 emissions by 65 crore kg. To sustain this momentum, continuous investment in multi-modal terminal integration is essential to fully realize the vision of an Atmanirbhar Bharat.


Question 2 (250 words): "The PM-Gati Shakti framework acts as a force multiplier for regional development." Evaluate this statement in the context of the recently approved railway expansion projects on the eastern coast.

The PM-Gati Shakti National Master Plan represents a paradigm shift from silo-based departmental functioning to an integrated infrastructure development model. The recent CCEA approval for the ₹9,450 crore railway multitracking projects across West Bengal, Odisha, Andhra Pradesh, and Tamil Nadu perfectly exemplifies this force multiplier effect for regional development.

Historically, infrastructure in India suffered from poor inter-ministerial coordination, leading to delays and cost overruns. By anchoring these 410 km railway projects on the Gati Shakti platform, the government ensures synchronized land acquisition, environmental clearances, and multi-modal integration. Economically, these lines—such as the 173 km Kharagpur-Bhadrak and the 90 km Gummidipundi-Gudur tracks—are vital economic arteries. They will facilitate a 76 MTPA surge in freight capacity, streamlining the evacuation of coal, cement, and steel from mineral-rich eastern states to southern consumption hubs.

Furthermore, this infrastructure push transcends pure industrial economics; it unlocks the socio-economic potential of the hinterland. By establishing efficient connectivity to ecologically rich and culturally significant sites like Pulicat Lake, Bhitarkanika National Park, and the Panchalingeswar Temple, it catalyses the local tourism economy. This aligns seamlessly with the objective of fostering self-employment and an 'Atmanirbhar' local population. Additionally, minimizing carbon emissions by 65 crore kg reflects a sustainable growth trajectory. Moving forward, ensuring digital tracking of project milestones up to the 2030-31 deadline will be imperative to translate this integrated planning into ground-level regional prosperity.


⚠️ Examiner Trap

Explain 3 common mistakes aspirants make on this topic.

  • Trap 1: Students often confuse the nodal ministry for PM-Gati Shakti. The correct fact is that while railways execute these projects, PM-Gati Shakti is monitored by the Department for Promotion of Industry and Internal Trade (DPIIT) under the Ministry of Commerce.
  • Trap 2: A common wrong assumption is that these projects are entirely Greenfield (new alignments). The reality is that these are multitracking (Brownfield) projects, adding 3rd and 4th lines to existing railway networks to ease congestion.
  • Trap 3: Many students miss the exact deadline and cost when answering questions on this topic. Always remember the total cost is ₹9,450 crore and the target completion year is 2030-31.

🧭 Exam Tip

For Prelims, examiners highly prefer testing the specific states covered (West Bengal, Odisha, Andhra Pradesh, Tamil Nadu) and geographical mapping of the connected tourist destinations (like Pulicat and Bhitarkanika). For Mains, GS Paper 3 questions will likely demand you to use this ₹9,450 crore project as a case study to validate the success of the PM-Gati Shakti master plan in reducing logistics costs. In interviews, expect questions on balancing infrastructure growth with environmental conservation. A high-probability Prelims question will focus on matching the specific railway lines (e.g., Gummidipundi–Gudur) with their respective states.